ROAD CONSTRUCTION UPDATE

Road Project Limits Start Date Finish Date Status
Andersonville Road Old White Lake Rd. to Township Border 5/26/2020 6/29/2020 Complete
Waldon Road Village to Clintonville Rd. 5/26/2020 7/7/2020 Complete
Sashabaw Road DTE to Oak Hill Rd. 6/29/2020 8/7/2020 Complete
Maybee Road Sashabaw Rd. to Clintonville Rd. 7/6/2020 8/10/2020 Complete
Sashabaw Road Maybee Rd. to the Waterford Border 7/13/2020 8/10/2020 Complete
Clintonville Road Waldon Rd. to Clarkston Rd. 8/5/2020 8/26/2020 Complete
Clintonville Road Maybee Rd. to Mann Rd. 8/4/2020 8/25/2020 Complete
Clintonville Road Maybee Rd. to Waldon Rd. 8/26/2020 9/25/2020 In Progress
Sashabaw Road Whipple Lake Canal, south of the   Sashabaw/Pine Knob Road intersection 8/11/2020 11/2/2020 Culvert Project In Progress
*** Project dates are all subject to change and will be updated as information becomes available ***